Construction Update: Aquitania

Aquitania

West Waterloo Place Liverpool Central Docks L3 0AY

Location: Liverpool

Prices From: £153000.00

Completion: Q2 2025

Aquitania

Introducing The Aquitania, the final phase of Central Docks, Liverpool Waters – a collection of 135 high-specification new build ‘waterside’ apartments and duplexes. Nestled in the heart of Liverpool’s £5 billion growth district, this development is part of the West Waterloo Place, offering a unique opportunity to become a vital part of the city’s newest and most vibrant waterfront community.

 

Located on an island site between the Leeds Liverpool Canal and the famous River Mersey, with views out into Liverpool Bay and the Irish Sea, these unique homes offer a sought-after sense of place and presence.

 

With phases 1, 2, and 3 sold out prior to completion, The Aquitania, phase 4, presents an unmissable chance for investors seeking prime properties in a thriving location. Anticipated for completion in Q1 2025 (subject to contract), this development promises a perfect blend of modern living and strategic positioning.

 

Secure parking options are available for purchase, enhancing the convenience for residents. The Aquitania is designed to meet the demand for high-quality waterside living, with its high-specification apartments and duplexes tailored for contemporary lifestyles.

 

Aquitania offers long-term residential apartments with an expected 6% yield! This opportunity is situated in the region of the city where capital growth will be the greatest.

 

West Waterloo Place is one of the most exciting and innovative developments ever to come to Liverpool. Offering waterside living of a superlative standard, just minutes from the beating heart of the city, it’s no surprise that the first and second phases sold before completion.

 

To learn more about an investment in Aquitania please contact us today.

Quarter 1 2025 Update

Quarter 4 2024 Update

This latest construction update for Aquitania outlines the following progress:

 

External Works:

Brickwork is complete up to Level 7.

Windows are fully installed from Levels 2 to 8.

Substation works are advancing.

 

Internal Works:

-Apartments are closing up floor by floor, with work currently

reaching Level 7.

-Plaster-boarding is complete on Level 2, with boarding on

Levels 3 to 5 and plastering set to commence shortly.

Quarter 3 2024 Update

This latest construction update for Aquitania outlines the following progress:

 

Phase 1 (Aquitania) is moving along nicely, and we’re making

great strides towards completion with the estimated completion

date April 2025.

 

On Phase 2 (Mauretania) we are currently planning to begin

piling work early in the new year. 

Quarter 2 2024 Update

This latest construction update for Aquitania outlines the following progress:

 

-All geotechnical and structural design detail for piling and marine piles are now completed

-Further assessment for bearing piles werer required and will be completed within the next 3weeks

-Steel frame design, drainage design will be completed within the next 4 weeks, following final ground investigation.

 

Quarter 1 2024 Update

This latest construction update for Aquitania outlines the following progress:

 

-All geotechnical and structural design detail for piling and marine piles are now completed

-Further assessment for bearing piles werer required and will be completed within the next 3weeks

-Steel frame design, drainage design will be completed within the next 4 weeks, following final ground investigation.

 

Quarter 3 2023 Update

This latest construction update for Aquitania outlines the following progress:

 

-All geotechnical and structural design detail for piling and marine piles are now completed

-Further assessment for bearing piles werer required and will be completed within the next 3weeks

-Steel frame design, drainage design will be completed within the next 4 weeks, following final ground investigation.

 

Quarter 2 2023 Update

This latest construction update for Aquitania outlines the following progress:

 

-The building’s regulation certificates are now approved and registered 

-Test piling has taken place and has been approved

-Drainage works have been undertaken 

-Steel supply will be delivered on-site on 12/06/23 

-Final approval from statutory authorities will allow piling works to commence

Quarter 1 2023 Update

This latest construction update for Aquitania outlines the following progress:

 

-Marine Piling commencing 5th June.

-Building piling due to commence end of June.

-Building tender documents finalised July.

-Anticipated building construction date 1st week September.

Get In Touch To Talk To One Of Our Experts About An Investment In This Property

Ready To Find Your Ideal Investment?

We can source any investment to fit your requirements

Please enter your requirements to discover the best options for you!

Thank you, a consultant will be in touch shortly. Click the X to continue browsing