Construction Update: Central Point

Central Point

Naylor Street Liverpool Merseyside L3 6DR

Location: Liverpool

Prices From: £140000.00

Completion: Q1 2025

Central Point

Central Point is located within the prime regeneration area of Vauxhall, Liverpool. 

 

This development is composed of 69 residential apartments over eight floors and made up of studio, one and two-bedroom apartments.

 

Rents are expected to yield 7.5%, and short-term lettings investors, yielding upwards of 10% p/a.

 

Central Point sits just a short walk from Liverpool City Centre and the World Heritage location of Albert Docks. We anticipate this development to have great appeal with short-term let investors due to the location close to the new £500m Everton Football Stadium, which will attract millions of new visitors to the city.

 

This residential development is located within a 10-minute walk from the busy Liverpool financial & business district, which is an attractive proposition for young professionals working in the city centre. It’s also an 8-minute walk to the Liverpool John Moores University Campus, attractive for overseas students studying in Liverpool.

 

To learn more about an investment in Central Point please contact us today.

Quarter 4 2024 Update

The groundworks have now been completed, and as you can see from the latest images, the concrete ground slab has fully cured according to our engineers’ specifications. This solid foundation is a crucial step in preparing for the upcoming construction phases, which are expected to begin shortly. With the groundwork set, the next stage will see the building rise steadily as we continue our efforts to deliver the project on time and on target.


Meanwhile, the design phase is advancing at a good pace. Our team is focused on finalising the detailed architectural and engineering plans, ensuring everything is ready for the next stages of construction. This involves close coordination between our designers, contractors, and project managers, making sure every aspect is well-prepared and aligned with the project’s goals. As we move into the next phase, we are confident that the project will continue to progress as planned.


In addition to the ongoing work on the Liverpool project, we are pleased to announce the completion of Bastion Point, which is now fully ready to welcome its first group of residents. Bastion Point, a smaller counterpart to our Central Point development, has reached a key stage with the final touches in place and all systems operational. This marks a significant step as we open the doors to a new community and prepare to welcome the first occupants into their homes.


Looking ahead, we are on track for the completion of Central Point next year. This project remains a central focus for the team, who are committed to delivering it to the highest standards.

Quarter 3 2024 Update

Advantage Investment is delighted to share the progress made onsite at Central Point over the past month.

 

Ten days ago, half of the ground floor slab was successfully poured and is currently curing as planned. This marks a crucial stage in the project timeline, and the progress is commendable. In line with the schedule, the shuttering pans have been erected, ensuring that the structure is being built according to detailed plans and specifications.

 

In addition to these developments, the lift shaft pits have already been poured, representing another key step in the project’s evolution. This achievement is pivotal as it lays the groundwork for the vertical transportation systems within the building.

 

Preparation for the next half of the ground floor slab has also been completed, and it is now ready for pouring. This stage is essential for maintaining the momentum of construction efforts and ensuring the timeline stays on track.

 

Moreover, substantial progress has been made in preparing several key walls. The ramp wall, the grid line 12/13 wall, and the interconnecting wall between Bastion Point and Central Point have all been prepped and are now ready for pouring. These preparations are crucial for the structural integrity and connectivity of the overall development.

Quarter 2 2024 Update

The excavation works in our Central Point development have reached an impressive 90% completion milestone. This pivotal phase has witnessed remarkable progress.

 

In parallel with the excavation, the substructure works have also progressed 

significantly, now standing at an impressive 90% completion rate. This phase is 

crucial in establishing the foundation for the structural integrity of Central Point, and I commend everyone involved for their tireless efforts.

 

The team has been making excellent progress in constructing the core walls below ground level. Currently, the bases and walls have reached a depth of 3.5 meters, marking an 80% completion rate.

 

Another significant milestone achieved is the completion of the concrete ring beam atop the core walls. This critical element plays a vital role in 

accommodating brickwork and reinforced concrete planks for the floor slab. 

 

This component is now 80% complete, showcasing our 

attention to detail and quality craftsmanship.

Quarter 1 2024 Update

As of the latest assessment, Central Point’s groundworks have reached an impressive 

 

completion rate of 65-70%. This significant progress underscores the dedication and efficiency of our team, who have been working tirelessly to ensure that all 

aspects of the groundworks are executed to the highest standards.

 

One of the notable achievements in this phase of the project is the construction of shear walls, which are essential for providing structural stability to the building. Additionally, the completion of lift pits marks another important milestone, laying the groundwork for the installation of elevators in the future.

 

Furthermore, the site has been meticulously prepared for the commencement of operations.

Quarter 4 2023 Update

The structural concrete frame is progressing well with the columns and shear walls almost complete. The formwork is all on site to form first floor transfer slab. With a large element of this also in place the pouring of the slab has also commenced.

 

Once this slab is complete the Steel Formed Structure (SFS) framing will hit site towards the end of July. This is a major milestone for the project as the external frame, along with the intermediate concrete floor slabs and roof will be poured progressively over the next couple of months.

 

In total there is in excess of 2800 cubic metres of reinforced concrete in the frame and transfer slab, forming a significant feat of design engineering in itself.

Quarter 4 2022 Update

Central Point is a brand new development, which will offer 67 residential apartments over seven floors, adding to the already stellar collection of buildings across Liverpool.

 

Comprised of 1, 2 and 3-bedroom apartments, Central Point sits just a short walk to Liverpool City Centre and the World Heritage location of Albert Docks

 

This investment is designed to cater for both long-term lettings investors, where rents are expected to yield 7.5%, and short-term lettings investors, yielding upwards of 10% p/a.

 

We anticipate this development to have great appeal with short-term let investors due to the location close to the new £500m Everton Football Stadium.

 
Get In Touch To Talk To One Of Our Experts About An Investment In This Property

Ready To Find Your Ideal Investment?

We can source any investment to fit your requirements

Please enter your requirements to discover the best options for you!

Thank you, a consultant will be in touch shortly. Click the X to continue browsing